20/11/2023

Expectations for 2024

  • Production. 200 MT per month (Q1), 250 MT per month (Q2), 300 MT per month (Q3) and 400 MT per month (Q4).
  • Processing plant. Order for the processing plant for the Lubumbashi site in the first quarter of 2024. This will increase margins.
  • Land packages. Start of the process of locking in land through option agreements for future large-scale mining.